What Is the Fixing Stage in Building? Victoria Guide

What Is the Fixing Stage in Building?

The fixing stage in building is the point in construction when a home’s internal linings and joinery are fitted and fixed in position, plasterboard, internal doors, architraves, skirting boards, built-in cabinetry, baths, basins and sinks. 

In Victoria it is one of the formal progress-payment stages set out in the Domestic Building Contracts Act 1995, sitting between the lock-up stage and practical completion.

Simply, the fixing stage marks the transition from structural work to interior finishing. Once it is signed off, your home stops looking like a building site and starts looking like a place you’ll live. 

At Xircon Homes, the fixing stage is one of six formal construction stages, each inspected before the matching progress payment falls due.

What happens during the fixing stage? 

During the fixing stage, all of a home’s internal cladding and fixed joinery are installed. This is the stage where the inside of the house takes a recognizable shape for the first time.

The work completed at the fixing stage typically includes:

  • Plasterboard linings fixed to walls and ceilings
  • Internal doors hung, along with door jambs
  • Architraves and skirting boards fitted
  • Kitchen and vanity cabinetry installed (usually excluding stone benchtops)
  • Built-in shelving and wardrobes fitted
  • Baths, basins, troughs and sinks fitted and fixed in position
  • Any internal staircase installed

It helps to know what has not happened yet. The fixing stage is not the same as the final finish. Painting, floor coverings, stone benchtops, splashbacks, shower screens, mirrors, tapware and power-point fit-offs all come later, during practical completion. 

At fixing, the components are fitted and fixed; at completion, they are finished and made functional. Because so many finishing trades converge here, the fixing stage is where your earlier design decisions become physical. Your cabinetry style, door profiles and joinery layout are all locked in well before this point.

The fixing stage is when your interior selections start becoming real. At Xircon Homes, your cabinetry, tiles, stone and flooring are confirmed early, so every finish installed at fixing is one you have already chosen and seen in person. Explore what comes standard in our premium new home inclusions package, then talk to our team about locking in your selections with confidence.

Fixing stage vs lock-up, frame and fit-off 

The fixing stage is one of several construction stages, and the names are easy to confuse. Each stage has a specific meaning under Victorian building law and in everyday builder language.

Stage What it means Key work
Frame stage The home’s frame is completed and approved by a building surveyor Wall frames and roof trusses erected; frame inspection
Lock-up stage (also called enclosed stage) The home’s external wall cladding and roof covering are fixed, flooring is laid, and external doors and windows are fixed Brickwork, roof, external doors and windows; home becomes weatherproof and securable
Fixing stage All internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted and fixed Plaster, joinery, cabinetry, internal doors, baths and basins
Fit-off (part of practical completion) Fixtures and fittings are connected and finished Tapware, power points, light fittings, toilets, door furniture, benchtops, splashbacks

The simplest way to remember the order: frame builds the skeleton, lock-up makes it weathertight, fixing installs the interior, and fit-off makes everything work. Fit-off is not a separate legal payment stage in Victoria — it falls within practical completion, the final stage before handover.

For the full sequence from base stage through to settlement day, read our step-by-step guide to the house construction phases in Melbourne, which walks through every stage and when each payment is due.

The legal definition of the fixing stage in Victoria 

In Victoria, the fixing stage has a precise legal definition. Under section 40 of the Domestic Building Contracts Act 1995 (Vic), the fixing stage means the stage when all internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards of a home are fitted and fixed in position.

This matters because the fixing stage is tied to a progress payment. Section 40 sets the standard stages for a major domestic building contract — deposit, base, frame, lock-up, fixing and completion — and caps the percentage of the contract price a builder can claim at each stage. 

Under the Act’s default schedule for a contract to build all stages, the fixing stage progress payment is 25% of the contract price.

Two points protect you as an owner. First, a builder cannot legally claim a stage payment before that stage is genuinely complete, and stages must be claimed in sequence. Second, if a contract uses a different payment schedule to the one in the Act, you must sign a specific statutory notice acknowledging the change before it applies.

(Source: Domestic Building Contracts Act 1995 (Vic), section 40, austlii.edu.au. Stage percentages apply to the Act’s default “build all stages” schedule; individual contracts may set different figures where the owner signs the prescribed notice. Confirmed current as of August 2026. Your own contract governs your payment stages — always check it, and seek advice from Consumer Affairs Victoria or a licensed professional for your specific situation.)

Award winning custom home builders in Melbourne

Still confused?

Understanding when each payment falls due removes much of the stress from a build. Xircon Homes builds on a fixed-price HIA contract with fixed site costs, so your progress payments follow the stages written into your contract with no surprises along the way. Book your site appraisal to get a clear, upfront picture of your build from base stage to handover.

Fixing stage checklist 

A fixing stage checklist helps you confirm the work is genuinely complete before you authorise the progress payment. Walk your site with your builder and check the following:

  1. Plasterboard is fixed to all walls and ceilings, with no obvious sheeting gaps
  2. Internal doors are hung and open and close cleanly
  3. Architraves and skirting boards are fitted throughout
  4. Kitchen and vanity cabinetry is installed and secured (stone benchtops usually follow at completion)
  5. Built-in wardrobes and shelving are fitted where specified
  6. Baths, basins, troughs and sinks are fitted and fixed in position
  7. Staircase (if applicable) is installed
  8. The stage is signed off and, where your contract requires it, inspected before payment

A quick tip from experience: do not withhold or release a stage payment based on a partial walkthrough. The fixing stage should be finalised, not “nearly there” before money changes hands. If something is incomplete, note it in writing and resolve it before the claim is paid.

A fixing stage should only pass when the work genuinely meets standard. Every Xircon Homes build is checked at each construction stage and backed by our 30-year structural guarantee, alongside three consecutive HIA awards in 2022, 2023 and 2024. Explore more about the top 20 home builders in Melbourne. 

How long does the fixing stage take? 

What happens during the fixing stage?

The fixing stage generally takes around three to five weeks, though the exact timeframe depends on the size and complexity of your home, the number of finishing trades involved, and how well those trades are scheduled.

Fixing is one of the most trade-dependent stages of a build. Plasterers, carpenters, cabinetmakers and joiners all work in a coordinated sequence, and delays here are most often caused by scheduling gaps rather than the work itself. A builder with strong subcontractor relationships and an experienced site supervisor manages these windows efficiently.

How long from the fixing stage to completion in Victoria? 

After fixing is signed off, most homes reach practical completion in roughly four to eight weeks. This final window covers painting, floor coverings, tiling, benchtops, and all electrical and plumbing fit-offs, followed by quality inspections and a building surveyor’s final inspection before your Certificate of Occupancy is issued.

(Disclaimer: These timeframes are general industry estimates for a standard single-storey Melbourne home. Actual durations vary with design complexity, site conditions, weather, trade availability and contract terms. Your builder’s construction program is the reliable guide for your specific build.)

Serving Melbourne families since 2013, Xircon Homes keeps the fixing stage moving with established trade relationships and an experienced site supervisor coordinating every finishing trade. Get in touch with our team to talk through your build timeline and design options.

What comes after the fixing stage? 

After the fixing stage comes practical completion, the final construction stage before handover. This is where your home is finished rather than just fitted out.

During practical completion, painting is completed, floor coverings and tiling are laid, stone benchtops are installed, and all electrical and plumbing fit-offs are connected. Shower screens, mirrors, splashbacks, door furniture and rails are fitted. 

Your builder’s quality team completes an internal inspection, a building surveyor conducts the final inspection, and settlement, the formal handover of your keys, generally follows within seven to 14 days.

If you are planning to build on your existing block, the same construction stages apply after demolition and approvals. You can see how it all fits together in our knockdown and rebuild process for Melbourne homeowners.

Frequently asked questions 

What is the difference between the lock-up stage and the fixing stage?

The lock-up stage is when the home’s external shell is complete and weatherproof — external wall cladding, roof covering, flooring, and external doors and windows are all fixed. The fixing stage comes next and covers the interior: plaster, internal doors, architraves, skirting, cabinetry, baths and basins fitted and fixed in position. Lock-up secures the outside; fixing installs the inside.

What is the enclosed stage in the building?

The enclosed stage describes the point where a home is closed in and weathertight — external walls, roof, doors and windows in place. In Victoria this is generally referred to as the lock-up stage under the Domestic Building Contracts Act 1995. “Enclosed” and “lock-up” describe the same milestone in most residential builds.

What is the frame stage in a building process?

The frame stage is when a home’s frame is completed and approved by a building surveyor. Wall frames and roof trusses are erected to define the shape and internal layout of the home. It comes after the base stage and before lock-up, and it is the point where you can first walk through your floor plan on site.

What does fit-off mean in building?

Fit-off means the installation and connection of a home’s fixtures and fittings — tapware, power points, light fittings, toilets, door handles and similar items. Fit-off happens during practical completion, after the fixing stage. It is when the components installed earlier are made functional and finished.

What is the fixing stage payment in Victoria?

Under the default schedule in section 40 of the Domestic Building Contracts Act 1995 (Vic) for a contract to build all stages, the fixing stage progress payment is 25% of the contract price. Contracts can set different percentages where the owner signs the prescribed statutory notice, so your own contract is the definitive guide. (Source: Domestic Building Contracts Act 1995 (Vic), s40. Verify against your contract.)

How long does the fixing stage take?

The fixing stage usually takes around three to five weeks for a standard single-storey home, depending on size, complexity and trade scheduling. From fixing sign-off to practical completion is generally another four to eight weeks. These are general estimates, your builder’s construction program gives the accurate timeframe for your build.

Is the fixing stage the same as fit-out?

Not exactly. “Fit-out” is a broad term for installing interior elements, while the fixing stage is a specific, legally defined construction stage in Victoria covering internal cladding and fixed joinery. Fit-off — the connection of fixtures and fittings — is a separate step that happens later, at practical completion.

Building a new home in Melbourne, or planning a knockdown rebuild on your current block? Xircon Homes guides you through every construction stage — from your first design conversation to the day you collect your keys. Contact the Xircon Homes team to start with a free site appraisal.